| Project and Designer Information: | |
| Region: | Central North Carolina |
| School Information:
Property (DSP) No: |
596 Student Elementary School
900-4334 |
| Architect: | LS3P Associates 2528 Independance, Wilmington, NC 28412 Phone: 910 790-9901 FAX: 910 790-3111 Email: [email protected] Web Site: http://www.boneyarch.com |
| Other Recent Prototype Locations: |
| Times Prototype has been Constructed : 2 |
| Construction Costs & Building Area: (Does not include, land, legal, design fees, testing or furnishings) |
|
| Date Bids Received: | 6/13/2000 |
| Construction Bid Cost: | $6,352,685.00 |
| Architectural Building Area: | 78900sq.ft. |
| Assignable Area | 56640sq.ft. |
| Assignable To Total Architectural Area Efficiency | 71.80% |
| Cost per Assignable Square Foot | $112.15 |
| Cost per Total Architectural Square Foot | $80.52 |
| Cost per Student | $10,658.87 |
| Special Costs Included in Bid | $857,990.00 |
| Description of Special Costs: On-Site Sewer, Off-Site Water Extension | |
| Special Features: | |
| Total Building Footprint (total all floors) Area | 77497sq.ft. |
| Site Acreage: | 42 |
| Construction Information: | |
| Building Code Construction Type: | Type IV UP |
| Construction Description: | Core Bldg-steel/CMU, CR Wing-light gauge steel |
| Roof: | High slope metal, low slope single ply |
| Number of Floors: | 1 |
| Number of Separate Buildings: | 2 |
| Heating Fuel: | Oil |
| Heating & Air Conditioning: | 2-Pipe Boiler & Chiller w/UV's |
| Technology Infrastructure: | Fiber Backbone/cable tray/Copper to CR |
| Design Consultants: | |
| Civil: | Davis-Martin-Powell & Assoc. High Point, NC 27262 |
| Structural: | Laurene Rickher Group Charlotte NC 282127 |
| Electrical: | United Engineering Group Charlotte NC 28212 |
| Plumbing/Mechanical: | United Engineering Group Charlotte NC 28212 |
| Other Consultant: | Foodesign Associates Charlotte NC 28227 |
| Designer and Owner Comments: |
| Designer Comments: The Elementary School prototype was conceived to meet 3 primary goals: site-adaptable design, reduced construction time from typical school construction & reduced bldg. cost from typical elem. schools. The Elementary School is separated into 2 distinct buildings.The media center/dining area, multi-purpose room, & admin. areas are constructed w/ conventional steel frame structure & masonry walls.These areas are separated from the classrm. wings & connected w/ enclosed covered corridors. Classrm. wings are attached but include 2 ramps between the 3 pods to adapt to grade variations on site. Classrm. wings are constructed using factory built light gauge steel stud wall panels & steel stud trusses. Panels are fabricated off-site & set in place as whole units.Roof trusses are similar. Masonry & metal roof are then applied in a conventional manner. Interior walls are finished w/ abuse-resistant gyp. bd. & ceramic tile. Approx. 2/3 of building is factory-built & not subject to weather delays.Time for construction is signficantly reduced.Cost is more than 10% lower than average cost for conventional methods. The school's base bid cost of $80.51 per s.f. includes all sitework, parking areas, media ctr furniture, kitchen equip, & built-in cabinets. |
| Owner Comments: |
Check to see if this school has its own Web Site? Click Here.
| | |
| | |
| | |
|