| Project and Designer Information: | |
| Region: | Eastern North Carolina |
| School Information:
Property (DSP) No: |
700 Student Elementary School
400-4736 |
| Architect: | Moseley Architects 3000 RDU Center Drive Suite 217, Raleigh, NC 27560 Phone: 919-840-0091 FAX: 919-840-0045 Email: [email protected] Web Site: http://www.moseleyarchitects.com |
| Other Recent Prototype Locations: |
| Times Prototype has been Constructed : 6 |
| Construction Costs & Building Area: (Does not include, land, legal, design fees, testing or furnishings) |
|
| Date Bids Received: | 11/18/2010 |
| Construction Bid Cost: | $13,215,450.00 |
| Architectural Building Area: | 80540sq.ft. |
| Assignable Area | 56600sq.ft. |
| Assignable To Total Architectural Area Efficiency | 70.28% |
| Cost per Assignable Square Foot | $233.49 |
| Cost per Total Architectural Square Foot | $164.09 |
| Cost per Student | $16,519.31 |
| Special Costs Included in Bid | $247,436.00 |
| Description of Special Costs: Kitchen Equipment Contract include in Total Construction Cost. | |
| Total Building Footprint (total all floors) Area | 80540sq.ft. |
| Site Acreage: | 46 |
| Construction Information: | |
| Building Code Construction Type: | II-B 2009 NCBC |
| Construction Description: | brick veneer with steel stud back up. Interior steel stud partitions finished with gypsum wall board. CMU walls are used in the corridors, gym, dining, kitchen, and mechanical areas. |
| Roof: | Standing Seam |
| Number of Floors: | 1 |
| Number of Separate Buildings: | 1 |
| Heating Fuel: | Propane |
| Heating & Air Conditioning: | 4 Pipe VAV |
| Design Consultants: | |
| Civil: | Timmons Group Raleigh, NC 27607 |
| Structural: | Stroud Pence and Associates Raleigh, NC 27609 |
| Electrical: | Progressive Design Collaborative Raleigh, NC 27609 |
| Plumbing/Mechanical: | Progressive Design Collaborative Raleigh, NC 27609 |
| Other Consultant: | Foodservice Consultant Ashland, VA 23005 |
| Designer and Owner Comments: |
| Designer Comments: The Elementary School is based on a K-5 prototype plan that was customized for the 4th & 5th grade intermediate school. The floor plan branches out into an "X" plan from a central rotunda space that provides for a view of the entire school from one location. The configuration provides good separation of bus and car drop off from play areas. The facility is LEED Gold certified. |
| Owner Comments: |
Check to see if this school has its own Web Site? Click Here.
| | |
| | |
| | |
|